Synopsis
Project name: Gresty Brook Health Care
Location: Crewe, Cheshire
Contract: JCT Intermediate with Contractor Design
Value: £621,000
Duration: 37 weeks
Summary:
Working within a live environment, phased works, exceptionally challenging logistics, whilst maintaining attention to architectural excellence are challenges to which this project was delivered with total effectiveness to all stakeholders.
During the last six months I have been working for Read at Gresty Brook, Crewe for Mr Neil Goode.
I have never felt the need to comment about Read’s contracts which I have worked on before but I feel this one is an exception. Renovating an old building, adding a flat roof extension to the rear, plus a two storey steel frame covered by a timber frame with a flat roof, surrounded by varying height parapets made this a task where co-operation of all the trades was of paramount importance.
Neil’s handling of this job has been exemplary from start to finish, he has remained cool, calm and courteous at all times.
For my part I have thoroughly enjoyed working for Neil as the atmosphere on site has been superb, it is many years since I tied myself virtually full time to a job, but maybe after years of housing sites this is the way forward for me.
Rarely do I feel the need to put pen to paper to express how I feel during a contract however this work has been truly pleasurable.